  1. All material delivery receiving to be taken after thorough inspection.

  2. No work to be commenced without Architecture and Civil Engineer’s approved drawing.

  3. Civil works to be done according to drawing only.

  4. Text-book standards to Mechanical, Electrical and Plumbing (MEP) drawings is maintained as closely as possible in real world situations, on our site.

  5. Use of Made-in-India and branded materials, wherever possible, is made mandatory.

  6. Cross ventilation, generous room dimensions, presence of natural light is strived for.

  7. Daily site visit by office staff tentatively from 10am to 12 pm and 6pm to 7pm.

Our Standard Operating Procedure

Standard Operating Procedures (SOPs) are an important structure providing feature of any organization. We at APSCON have an SOP’s regarding construction, file maintenance in office and organizational functioning, overall.

SOPs in Office

  1. Works are divided on basis of “Request for Proposal”, and we strive to receive a minimum of three written proposals for each work.

  2. All contractors for all works require to submit quotations against Request for Proposals (RFP) to obtain a work order.

  3. No Civil Contractor to be entertained without a final written quotation

  4. Realistic project timelines to be said and achieved.

  5. Two visits on site per day.

  6. All bills are recorded and processed within 3 days of work completion.